Installation - JuiceBox® Legacy

This procedure explains how to install one charging station onto the stand. If applicable, perform the same procedure for both charging stations.

This procedure applies only to "JuiceBox Legacy". Verify the correct product before installing.
Note:
  • The JuiceStand must be installed in accordance with the National Electrical Code (NFPA 70) and all applicable local jurisdiction requirements.
  • Junction Boxes must be UL Listed or UL Certified for outdoor-use.
  • Conduit fittings must be liquid-tight and UL Listed or UL Certified for outdoor-use.
  1. Secure the JuiceStand Pro to the ground stud anchors (refer to Installation Area for more information).
  2. Secure the crossbars to the stand.
         Note: It is recommended to apply a torque of 25 in lbs to the screws.
  3. Secure the backplate to the charging station.
         Note: It is recommended to apply a torque of 25 in lbs to the screws.
     Note: In the next step, the backplate and charging station are handled as an assembly.
  1. Secure the backplate and charging station assembly to the crossbars.
         Note: It is recommended to apply a torque of 21 in lbs to the screws.